Updates

2022 project construction is underway.

Friday, May 13, 2022

During the coming week, crews will work in the following areas:

  • Hadley/Hastings Avenue, between Gary Boulevard and Pullman Avenue.
    • Installation and material staging.
    • Shifting lanes, two-way traffic allowed.
    • Parking restrictions.
    • Local residences will remain accessible.
  • West Point Douglas Road, between the 80th Street overpass and the Youth Service Bureau.
    • Roadway restoration.
    • One-way, alternating flagged traffic.
    • Local businesses will remain accessible.

Please note that construction schedules are subject to change.


Friday, May 6, 2022

Major construction activities for 2022 begin the week of May 9, 2022.

During the coming week, crews will work in the following areas. Please use caution as crews will be delivering materials and staging equipment along the project route.

  • Hastings Avenue and 1st Street.
    • Natural gas testing activities.
    • Access to local businesses will remain accessible.
  • 8th Avenue, between Laurel and Hastings avenues.
    • Installation and material staging.
    • Eastbound shoulder closure.
    • Access to local residences will remain accessible. Please use 9th Avenue for alley access.
  • Hadley Avenue, between Scott and Gary boulevards.
    • Installation and material staging.
    • Northbound shoulder closure.
  • West Point Douglas Road, between the 80th Street overpass and the Youth Service Bureau.
    • Roadway restoration.
    • One-way, alternating flagged traffic.
    • Access to local businesses will remain accessible.

Please note that construction schedules are subject to change.


Friday, April 29, 2022

This year’s construction is anticipated to start the week of May 9, 2022.

In the weeks prior to start of construction, you can expect to see increased activity along the project route to prepare for construction, including:

  • Marking of underground utility lines.
  • Increased construction traffic.
  • Preparation and delivery of materials to staging areas.
  • Traffic control measures being implemented.

The project will take place in the following areas:

  • Hastings Avenue, between Gary Boulevard and 1st Street.
  • Belden Boulevard, between West Point Douglas Road and Hadley Avenue.
  • East Point Douglas Road, between 90th Street and East Point Douglas Road.

As we approach the start of construction, we will provide additional updates.

Please note schedules are subject to change.


Archived Updates