Friday, Nov. 11, 2022
During the coming week, crews will work in the following areas:
- 8th Avenue, between Laurel and Hastings avenues.
- Restoration activities.
- Belden Boulevard, between Hadley Avenue and West Point Douglas Road.
- Restoration activities.
- East Point Douglas Road, between East Point Douglas Road and 90th Street.
- Restoration activities.
- 90th Street, between East Point Douglas Road and Indahl Avenue.
- Restoration activities.
Local residences and businesses will remain accessible. Schedules are subject to change.
Friday, Nov. 4, 2022
During the coming week, crews will work in the following areas:
- Belden Boulevard/West Point Douglas Road, between Hadley Avenue and the Youth Service Bureau.
- Restoration activities.
- Local residences and businesses will remain accessible.
- East Point Douglas Road, between East Point Douglas Road and 90th Street.
- Mobile work areas with lane closures and lane shifts, two-way traffic allowed.
- Restoration activities.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Oct. 28, 2022
Crews have completed natural gas line installation. We will continue to perform natural gas testing activities and restoration work during the coming weeks.
During the coming week, crews will work in the following areas:
- Hastings/Hadley Avenue, between Portland and Scott Boulevard.
- Roadway restoration activities.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Belden Boulevard/West Point Douglas Road, between Hadley Avenue and the Youth Service Bureau.
- Full road closure.
- Restoration activities.
- Local residences and businesses will remain accessible.
- East Point Douglas Road, between East Point Douglas Road and 90th Street.
- Mobile work areas with land closures and lane shifts, two-way traffic allowed.
- Restoration activities.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Oct. 21, 2022
During the coming week, crews will work in the following areas:
- Hastings/Hadley Avenue, between Portland and Scott Boulevard.
- Roadway restoration activities.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Belden Boulevard/West Point Douglas Road, between Hadley Avenue and the Youth Service Bureau.
- Full road closure.
- Natural gas line installation, equipment staging and restoration activities.
- Local residences and businesses will remain accessible.
- East Point Douglas Road, between East Point Douglas Road and 90th Street.
- Mobile work areas with lane shifts, two-way traffic allowed.
- Restoration activities.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Oct. 14, 2022
During the coming week, crews will work in the following areas:
- Hastings/Hadley Avenue, between Portland and Scott Boulevard.
- Roadway restoration activities.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Belden Boulevard/West Point Douglas Road, between Hadley Avenue and the Youth Service Bureau.
- Full road closure.
- Natural gas line installation, equipment staging and restoration activities.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Oct. 7, 2022
During the coming week, crews will work in the following areas:
- Hastings/Hadley Avenue, between Portland Avenue and Scott Boulevard.
- Restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Belden Boulevard/West Point Douglas Road, between Hadley Avenue and the Youth Service Bureau.
- Full road closure.
- Natural gas line installation and equipment staging.
- Local residences and businesses will remain accessible.
- Intersection of Hadley Avenue and Belden Boulevard.
- Single-day road closure during the week of Oct. 10, 2022.
- Local residences and businesses will remain accessible.
- Follow posted detours.
- Belden Boulevard, between Grenadier and Hadley avenues.
- Full road closure.
- Equipment staging.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Sept. 30, 2022
Crews have installed approximately 95% of this year’s natural gas main line. We will continue to share progress with you during construction.
During the coming week, crews will work in the following areas:
- Hastings/Hadley Avenue, between Portland Avenue and Scott Boulevard.
- Restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Intersection of Hastings and 8th avenues.
- Natural gas testing activities.
- Shoulder closure.
- Local residences and businesses will remain accessible.
- You may smell natural gas outside in this area during this work. You should not smell natural gas indoors.
- If you ever suspect a natural gas leak, leave your home or business immediately. Once you are safely away, call 911, then Xcel Energy at 800-895-2999.
- It is important to know how to recognize potentially dangerous natural gas leaks, so use your senses. Signs of a natural gas leak include:
- A “rotten egg” or sulfur-like odor, although it may smell differently to you.
- Hissing, whistling or roaring sounds outside near the natural gas line or inside near an appliance.
- Dirt spraying into the air or continuous bubbling in a pond or creek.
- Unexplained dead or dying vegetation.
- Intersection of Hadley Avenue and Scott Boulevard.
- Natural gas testing activities.
- Shoulder closure.
- Local residences and businesses will remain accessible.
- You may smell natural gas outside in this area during this work. You should not smell natural gas indoors.
- If you ever suspect a natural gas leak, leave your home or business immediately. Once you are safely away, call 911, then Xcel Energy at 800-895-2999.
- It is important to know how to recognize potentially dangerous natural gas leaks, so use your senses. Signs of a natural gas leak include:
- A “rotten egg” or sulfur-like odor, although it may smell differently to you.
- Hissing, whistling or roaring sounds outside near the natural gas line or inside near an appliance.
- Dirt spraying into the air or continuous bubbling in a pond or creek.
- Unexplained dead or dying vegetation.
- Belden Boulevard/West Point Douglas Road, between Hadley Avenue and the Youth Service Bureau.
- Full Road Closure starting Tuesday, Oct. 4, 2022, and lasting for 3 weeks.
- Natural gas line installation and equipment staging.
- Local residences and businesses will remain accessible.
- Belden Boulevard, between Grenadier and Hadley avenues.
- Shoulder closure.
- Equipment staging.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Sept. 23, 2022
Crews have installed approximately 90% of this year’s natural gas main line. We will continue to share progress with you during construction.
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Summit and Broadway avenues.
- Installation, material staging and restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Portland and 8th avenues.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Belden Boulevard, between Grenadier Avenue and West Point Douglas Road
- Equipment staging.
- Shoulder closure.
- Local residences and businesses will remain accessible.
- A full closure of Belden Boulevard, between Hadley Avenue and West Point Douglas Road will begin starting as early as Oct. 4 and last for up to 3 weeks.
Please note that construction schedules are subject to change.
Friday, Sept. 16, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Pleasant and Summit avenues.
- Restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation, material staging and restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Portland and Aurora avenues.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Sept. 9, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Pleasant and Summit avenues.
- Restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation, material staging and restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Portland and Aurora avenues.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Sept. 2, 2022
In observance of Labor Day, crews will not work on Monday, Sept. 5, 2022.
Crews have installed approximately 70% of this year’s natural gas main line. We will continue to share progress with you during construction.
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Pleasant and Summit avenues.
- Restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation, material staging and restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Portland and Aurora avenues.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Aug. 26, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Pleasant and Summit avenues.
- Installation, material staging and restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation, material staging and restoration.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between 77th Street and Lincoln Avenue.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, Aug. 19, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Pleasant and Summit avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between 77th Street and Portland Avenue.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- 8th Avenue, between Laurel and Hastings avenues.
- Installation, material staging and restoration.
- Eastbound shoulder closures.
- Access to local residences will remain accessible. Please use 9th Avenue for alley access.
Please note that construction schedules are subject to change.
Friday, Aug. 12, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between Pleasant and Summit avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between 77th Street and Portland Avenue.
- Installation, material staging and restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- 8th Avenue, between Laurel and Hastings avenues.
- Installation, material staging and restoration.
- Eastbound shoulder closures.
- Access to local residences will remain accessible. Please use 9th Avenue for alley access.
Please note that construction schedules are subject to change.
Friday, Aug. 5, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue cul-de-sac and 1st Street.
- Installation and material staging.
- Shifting work areas.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Pleasant and Summit avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between 77th Street and Portland Avenue.
- Installation, material staging and temporary restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, July 29, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue cul-de-sac and 1st Street
- Installation and material staging.
- Shifting work areas.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Pleasant and Summit avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hastings Avenue, between Summit and Broadway avenues.
- Installation and material staging.
- One-way, alternating flagged traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between 77th Street and Selby Avenue.
- Installation, material staging and temporary restoration.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, July 22, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, July 15, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, July 8, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, July 1, 2022
In observance of Independence Day, crews will not work on Monday, July 4, 2022.
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, June 24, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, June 17, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, June 10, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Lawrence Drive.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, June 3, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- One-way, alternating signaled traffic.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and McCammon Avenue.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, May 27, 2022
In observance of Memorial Day, crews will not work on Monday, May 30, 2022.
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Pullman Avenue.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, May 20, 2022
During the coming week, crews will work in the following areas:
- Hastings Avenue, between 1st Street and Pleasant Avenue.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
- Hadley/Hastings Avenue, between Gary Boulevard and Pullman Avenue.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences and businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, May 13, 2022
During the coming week, crews will work in the following areas:
- Hadley/Hastings Avenue, between Gary Boulevard and Pullman Avenue.
- Installation and material staging.
- Shifting lanes, two-way traffic allowed.
- Parking restrictions.
- Local residences will remain accessible.
- West Point Douglas Road, between the 80th Street overpass and the Youth Service Bureau.
- Roadway restoration.
- One-way, alternating flagged traffic.
- Local businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, May 6, 2022
Major construction activities for 2022 begin the week of May 9, 2022.
During the coming week, crews will work in the following areas. Please use caution as crews will be delivering materials and staging equipment along the project route.
- Hastings Avenue and 1st Street.
- Natural gas testing activities.
- Access to local businesses will remain accessible.
- 8th Avenue, between Laurel and Hastings avenues.
- Installation and material staging.
- Eastbound shoulder closure.
- Access to local residences will remain accessible. Please use 9th Avenue for alley access.
- Hadley Avenue, between Scott and Gary boulevards.
- Installation and material staging.
- Northbound shoulder closure.
- West Point Douglas Road, between the 80th Street overpass and the Youth Service Bureau.
- Roadway restoration.
- One-way, alternating flagged traffic.
- Access to local businesses will remain accessible.
Please note that construction schedules are subject to change.
Friday, April 29, 2022
This year’s construction is anticipated to start the week of May 9, 2022.
In the weeks prior to start of construction, you can expect to see increased activity along the project route to prepare for construction, including:
- Marking of underground utility lines.
- Increased construction traffic.
- Preparation and delivery of materials to staging areas.
- Traffic control measures being implemented.
The project will take place in the following areas:
- Hastings Avenue, between Gary Boulevard and 1st Street.
- Belden Boulevard, between West Point Douglas Road and Hadley Avenue.
- East Point Douglas Road, between 90th Street and East Point Douglas Road.
As we approach the start of construction, we will provide additional updates.
Please note schedules are subject to change.
Friday, April 15, 2022
We want to thank everyone who attended the South Washington Natural Gas Project virtual open house this past Wednesday.
If you were unable to attend the virtual open house and would like to learn more about the project, you can view the presentation and a recording of the meeting here. If you have additional questions about to the project, do not hesitate to contact us.
Minor construction activities will occur in April to prepare for construction. Major construction activities will start in May. The project will take place in the following areas:
- Hastings Avenue, between Gary Boulevard and 1st Street.
- Belden Boulevard, between West Point Douglas Road and Hadley Avenue.
- East Point Douglas Road, between 90th Street and East Point Douglas Road.
As we approach the start of construction, we will provide additional updates.
Please note that construction schedules are subject to change.
Friday, April 8, 2022
You’re invited to our virtual open house!
Please join us to learn more about project construction in 2022.
- Date: Wednesday, April 13, 2022
- Time: 6 p.m. – 7 p.m.
- Join online: Click Here
- Dial-in number: 855-962-1519
Can’t make it? We’ll post the virtual open house presentation on our website following the live event.
This year’s construction activities will start in May 2022 and will take place in the following areas:
- Hastings Avenue, between Gary Boulevard and 1st Street.
- Belden Boulevard, between West Point Douglas Road and Hadley Avenue.
- East Point Douglas Road, between 90th Street and East Point Douglas Road.
As we approach the start of construction, we will provide additional updates.
Please note that construction schedules are subject to change.
Friday, April 1, 2022
You’re invited to our virtual open house to learn more about project construction in 2022.
- Date: Wednesday, April 13, 2022
- Time: 6 p.m. – 7 p.m.
- Join online: Click Here
- Dial-in number: 855-962-1519
Can’t make it? We’ll post the virtual open house presentation and recording following the live event.
Click here to learn more about the virtual open house.
We are currently planning and permitting 2022 construction which will start in May and be constructed on Hastings Avenue, between Gary Boulevard and 1st Street
We will keep you informed prior to the start of construction.
Wednesday, Dec. 1, 2021
We have completed this year’s natural gas construction. It was our pleasure to work in your neighborhood, and we thank you for your patience and cooperation.
Construction will resume in spring 2022 on Hastings Avenue, between Gary Boulevard and 1st Street.
We will keep you informed prior to the start of next year’s construction.
Friday, Oct. 29, 2021
We have completed this year’s natural gas construction. It was our pleasure to work in your neighborhood, and we thank you for your patience and cooperation.
Minor restoration activities will continue through the coming weeks. Construction will resume in spring 2022 on Hastings Avenue, between Gary Boulevard and 1st Street.
We will keep you informed prior to the start of next year’s construction.
Friday, Oct. 22, 2021
We’ve successfully completed line installation for 2021. We will restore work areas through October.
During the coming week, work will occur in the following areas:
- West Point Douglas Road, near the Youth Service Bureau.
- Restoration and construction.
- Lane shifts may occur.
- Hadley/Hastings Avenue, between Scott and Gary boulevards.
- Restoration.
- Activities in roadway shoulder.
Schedules are subject to change.
To learn more about construction happening in Cottage Grove, visit their website.
Friday, Oct. 15, 2021
During the coming week, construction will occur in the following areas:
- East Point Douglas Road, between 92nd Street and Menards.
- Construction and restoration.
- Activities in the roadway shoulder.
- 90th Street, between East Point Douglas Road and Indahl Avenue.
- Construction and restoration.
- Activities in roadway shoulder.
- Belden Boulevard/West Point Douglas Road, between Hadley/Hastings Avenue and 7900 West Point Douglas Road.
- Construction and restoration.
- Shifting lanes.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
Schedules are subject to change.
To learn more about construction happening in Cottage Grove, visit their website.
Friday, Oct. 8, 2021
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between the Pointe West Business Center Office Park and Irwin Avenue.
- Restoration.
- West Point Douglas Road, between the Youth Service Bureau and 7900 West Point Douglas Road.
- Construction and restoration.
- Shifting lanes may occur.
- Belden Boulevard/West Point Douglas Road, between Hadley/Hastings Avenue and the Youth Service Bureau.
- Restoration.
- Full road closure from Monday, Oct. 11, 2021, through Friday, Oct. 15, 2021.
- Follow posted detours.
- Businesses will remain accessible.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
Schedules are subject to change.
To learn more about construction happening in Cottage Grove, visit their website.
Friday, Oct. 1, 2021
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between the Pointe West Business Center Office Park and Irwin Avenue.
- Line installation and equipment staging.
- Testing activities.
- Local traffic only.
- West Point Douglas Road, between Belden Boulevard and 7900 West Point Douglas Road.
- Construction and restoration.
- Shifting lanes may occur.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
- Hadley/Hastings Avenue, between Scott and Gary boulevards.
- Construction and restoration.
- Work in roadway shoulder.
Schedules are subject to change.
To learn more about construction happening in Cottage Grove, visit their website.
Friday, Sept. 24, 2021
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between the Pointe West Business Center Office Park and Irwin Avenue.
- Line installation and equipment staging.
- Testing activities.
- Local traffic only.
- West Point Douglas Road, between Belden Boulevard and 7900 West Point Douglas Road.
- Construction and restoration.
- Shifting lanes may occur.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
- Hadley/Hastings Avenue, between Scott and Gary boulevards.
- Line installation and equipment staging.
- Work in roadway shoulder.
Schedules are subject to change.
To learn more about construction happening in Cottage Grove, visit their website.
Friday, Sept. 17, 2021
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between the Pointe West Business Center Office Park and Irwin Avenue.
- Line installation and equipment staging.
- Local traffic only.
- West Point Douglas Road, between Belden Boulevard and 7900 West Point Douglas Road.
- Construction and restoration.
- Shifting lanes may occur.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
- Hadley/Hastings Avenue, between Scott and Gary boulevards.
- Work in roadway shoulder.
- Equipment staging.
- Testing preparation.
Construction schedules are subject to change.
To learn more about construction happening in Cottage Grove, visit their website.
Friday, Sept. 10, 2021
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between the Pointe West Business Center Office Park and Irwin Avenue.
- Line installation and equipment staging.
- Local traffic only.
- West Point Douglas Road, between Belden Boulevard and 7900 West Point Douglas Road.
- Construction and restoration.
- Shifting lanes may occur.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
- Hadley/Hastings Avenue, between Scott and Gary boulevards.
- Work in roadway shoulder.
- Equipment staging.
- Testing preparation.
Construction schedules are subject to change.
To learn more about projects happening in Cottage Grove, visit their website.
Friday, Sept. 3, 2021
In observance of Labor Day, crews will not work Sunday, Sept. 5, 2021, and Monday, Sept. 6, 2021. Construction will resume on Tuesday, Sept. 7, 2021.
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between Jamaica and Irwin avenues.
- Line installation and equipment staging.
- Local traffic only.
- West Point Douglas Road, between the Belden Boulevard and 7900 West Point Douglas Road.
- Construction and restoration activities.
- Shifting lanes may occur.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
Construction schedules are subject to change.
To learn more about projects happening in Cottage Grove, visit their website.
Friday, Aug. 27, 2021
We have installed more than 80 percent of this year’s natural gas line. We will continue to share progress with you during construction.
During the coming week, construction will occur in the following areas:
- West Point Douglas Road, between Jamaica and Irwin avenues.
- Line installation and equipment staging.
- West Point Douglas Road, between the Youth Service Bureau and 7900 West Point Douglas Road.
- Restoration activities.
- Belden Boulevard, between Hadley/Hastings and Grenadier avenues.
- Equipment and line staging.
Construction schedules are subject to change.
To learn more about projects happening in Cottage Grove, visit their website.
Friday, Aug. 20, 2021
During the week of Aug. 23, 2021, crews will work in the following areas:
West Point Douglas Road, between Jamaica and Irwin avenues. Shifting lanes will occur for equipment staging and construction. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between the Youth Service Bureau and 7900 West Point Douglas Road. Shifting lanes will be in place for restoration. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. A full road closure will be in place through early September 2021. Sites will remain accessible.
Belden Boulevard, between Hadley/Hastings and Grenadier avenues. A shoulder closure will occur to stage natural gas line and equipment. Sites will remain accessible.
Hadley/Hastings Avenue, between Scott and Belden boulevards. Shifting lanes and street parking restrictions may occur. Sites will remain accessible.
Intersection of Hadley/Hastings Avenue and Belden Boulevard. The road will be fully closed for one day during the week of Aug. 23, 2021. Through traffic should follow posted detours. Local traffic will be allowed, and sites will remain accessible.
Construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, Aug. 13, 2021
During the week of Aug.16, 2021, crews will work in the following areas:
West Point Douglas Road, between Jamaica and Irwin avenues. Shifting lanes on West Point Douglas Road will occur for equipment staging and natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between the Youth Service Bureau and 7900 West Point Douglas Road. Shifting lanes will be in place for natural gas line installation and restoration of work areas. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. A full road closure will be in place for three weeks for natural gas line installation. Sites will remain accessible.
Hadley Avenue/Hastings Avenue, between Scott and Belden boulevards. Natural gas line installation will occur. Street parking may be restricted. Sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, Aug. 6, 2021
During the week of Aug. 9, 2021, crews will work in the following areas:
West Point Douglas Road, between Belden Boulevard and Extra Space Storage. Shifting lanes will occur for natural gas line installation and restoration of work areas. Local traffic will be allowed, and sites will remain accessible.
Hadley Avenue/Hastings Avenue, between Scott and Belden boulevards. Natural gas line installation will occur. Street parking may be restricted. Sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, July 30, 2021
Crews have installed more than 60 percent of this year’s natural gas line. We will continue to share progress with you during the project.
During the week of Aug. 2, 2021, crews will work in the following areas:
West Point Douglas Road, between Jamaica and Irwin avenues. Shifting lanes on West Point Douglas Road will occur for equipment staging and natural gas line installation. No traffic impacts will occur to Jamaica Avenue. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and Extra Space Storage. Shifting lanes will occur for natural gas line installation and restoration of previous work areas. Local traffic will be allowed, and sites will remain accessible.
Hadley Avenue/Hastings Avenue, between Scott and Belden boulevards. Natural gas line installation will occur in this area. Street parking may be restricted. Sites will remain accessible.
90th Street, between East Point Douglas Road and Indahl Avenue. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, July 23, 2021
During the week of July 26, 2021, crews will work in the following areas:
West Point Douglas Road and Jamaica Avenue. Shifting lanes on West Point Douglas Road to the west of Jamaica Avenue will occur for natural gas line installation. There will be no traffic impacts to Jamaica Avenue. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and 7900 West Point Douglas Road. Shifting lanes will occur for natural gas line installation and restoration of previous work areas. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railroad tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews have staged natural gas line for installation this summer. There may be some temporary traffic impacts as crews work in this area.
Hadley Avenue/Hastings Avenue, between Scott and Belden boulevards. Natural gas line installation will occur in this area. Street parking may be restricted. Sites will remain accessible.
East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
90th Street, between East Point Douglas Road and Indahl Avenue. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, July 16, 2021
During the week of July 19, 2021, crews will work in the following areas:
West Point Douglas Road and Jamaica Avenue. Shifting lanes on West Point Douglas Road to the west of Jamaica Avenue will occur for natural gas line installation. There will be no traffic impacts to Jamaica Avenue. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and 7900 West Point Douglas Road. Shifting lanes will occur for natural gas line installation and restoration of previous work areas. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railroad tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews have staged natural gas line for installation this summer. There may be some temporary traffic impacts as crews work in this area.
East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
90th Street, between East Point Douglas Road and Indahl Avenue. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, July 9, 2021
Crews continue to make progress for this year’s natural gas line work, having installed about 50 percent of this year’s line. We will provide updates throughout the project.
During the week of July 12, 2021, crews will work in the following areas:
West Point Douglas Road, between Belden Boulevard and the South Washington Public Schools Transportation Department. Shifting lanes will occur for natural gas line installation and restoration of previous work areas. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railroad tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews have staged a natural gas line for installation in this area this summer. There may be some temporary traffic impacts as crews work in this area.
East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
90th Street, between East Point Douglas Road and Indahl Avenue. Shifting lanes will occur for the marking of utility lines and “potholing” to verify their locations. We will stage natural gas line ahead of installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, July 2, 2021
In observance of Independence Day, crews will not work Saturday, July 3, 2021, through Monday, July 5, 2021. Construction activities will resume on Tuesday, July 6, 2021.
During the week of July 6, 2021, crews will work in the following areas:
West Point Douglas Road, between Extra Space Storage and the South Washington Public Schools Transportation Department. Shifting lanes will occur for natural gas line installation and restoration of previous work areas. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews are staging natural gas line to prepare it for installation in this area this summer. There may be some temporary traffic impacts as crews unload the pipe from trucks.
East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, June 25, 2021
Staying safe around construction areas
To ensure your safety and the safety of our crews, please take the following steps while traveling near and through work areas:
- Watch for construction crews and equipment.
- Do not enter work areas.
- Follow all construction signage and direction from crews.
- Reduce speeds.
- Be aware! Traffic control measures change regularly.
- Refrain from using your cell phone while driving.
During the week of June 28, 2021, crews will work in the following areas:
West Point Douglas Road, between Extra Space Storage and the South Washington Public Schools Transportation Department. Shifting lanes will occur for natural gas line installation and restoration of previous work areas. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews are staging natural gas line to prepare it for installation in this area this summer. There may be some temporary traffic impacts as crews unload the pipe from trucks.
East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, June 18, 2021
Our crews continue to make great progress for this year’s construction activities, installing approximately 5,300 feet of natural gas line. We will provide progress updates throughout the project.
During the week of June 21, 2021, crews will work in the following areas:
West Point Douglas Road, between the South Washington Public Schools Transportation Department and Jamaica Avenue. Natural gas line installation has been completed. Crews will restore previous work areas over the coming weeks.
West Point Douglas Road, between 7900 West Point Douglas Road and the South Washington Public Schools Transportation Department. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews are staging natural gas line to prepare it for installation in this area this summer. There may be some temporary traffic impacts as crews unload the pipe from trucks.
East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, June 11, 2021
During the week of June 14, 2021, crews will work in the following areas:
West Point Douglas Road, between Jamaica and Islay avenues. We will restore previous work areas over the coming weeks.
West Point Douglas Road, between the South Washington Public Schools Transportation Department and Jamaica Avenue. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews may start placing natural gas line to prepare it for installation in this area this summer. There may be some temporary traffic impacts as crews unload the pipe from trucks.
Construction on East Point Douglas Road, between East Point Douglas Road and Hillside Trail. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Please note that construction schedules are subject to change.
Several construction projects are taking place this year in Cottage Grove including construction of the CAPP Industries Warehouse Project on West Point Douglas Road. To learn more about projects happening in the city, click here to visit their website.
Friday, June 4, 2021
During the week of June 7, 2021, crews will work in the following areas:
From the southern project endpoint near Miller Road South and the railroad tracks to 96th Street near West Point Douglas Road. Natural gas line installation has been completed. Crews will restore previous work areas over the coming weeks.
West Point Douglas Road, between Islay Avenue and 96th Street. West Point Douglas Road will be closed to through traffic in this area. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Jamaica and Islay avenues. Shifting lanes will occur for natural gas line installation. Sites will remain accessible.
West Point Douglas Road, between the South Washington Public Schools Transportation Department and Jamaica Avenue. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews may start placing natural gas line to prepare it for installation in this area this summer. There may be some temporary traffic impacts as crews unload the pipe from trucks.
Please note that construction schedules are subject to change.
Thursday, May 27, 2021
In observance of Memorial Day, crews will not work Sunday, May 30, 2021, and Monday, May 31, 2021. Construction activities will resume on Tuesday, June 1, 2021.
During the week of June 1, 2021, crews will work in the following areas:
From the southern project endpoint near Miller Road South and the railroad tracks to 96th Street near West Point Douglas Road. Natural gas line installation has been completed. Crews will restore previous work areas over the coming weeks.
West Point Douglas Road, between Islay Avenue and 96th Street. West Point Douglas Road will be closed to through traffic in this area. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Jamaica and Islay avenues. Shifting lanes will occur for natural gas line installation. Sites will remain accessible.
West Point Douglas Road, between Belden Boulevard and the Youth Service Bureau. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews may start placing natural gas line to prepare it for installation in this area this summer. There may be some temporary traffic impacts as crews unload the line from trucks.
Please note that construction schedules are subject to change.
Friday, May 21, 2021
We are pleased that this project is underway. After our first full week of construction, our crews have made great progress in our installation of the project’s natural gas line. We will keep you posted on progress as the project moves forward.
During the week of May 24, 2021, crews will work in the following areas:
From the southern project endpoint near Miller Road South and the railroad tracks to 96th Street near West Point Douglas Road. Crews will work to complete the natural gas line installation in this area.
West Point Douglas Road, between Islay Avenue and 96th Street. West Point Douglas Road will be closed to through traffic. Local traffic will be allowed, and sites will remain accessible.
West Point Douglas Road, between Jamaica and Islay avenues. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
Between Highway 61/Highway 10 and the railway tracks north of the intersection of West Point Douglas Road and Belden Boulevard. Crews may start laying natural gas line and preparing it for installation in this area later this summer. There may be some temporary traffic impacts as crews unload the line from trucks, but no other traffic impacts are anticipated until later this summer.
Please note that construction schedules are subject to change.
Friday, May 14, 2021
During the week of May 17, 2021, crews will work in the following areas:
- From the southern project endpoint near Miller Road South and the railroad tracks to 96th Street near West Point Douglas Road. Crews will conduct natural gas line installation in this area.
- West Point Douglas Road, between Islay Avenue and 96th Street. West Point Douglas Road will be closed to through traffic. Local traffic will be allowed, and sites will remain accessible.
- West Point Douglas Road, between Jamaica and Islay avenues. Shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
- Highway 61/Highway 10, between Jamaica Avenue and halfway between the Jamaica and Keats avenues exits. Short-term shoulder closures and shifting lanes will occur for crews to install concrete barriers along the southbound shoulder of Highway 61/Highway 10. The barriers will separate crews working on West Point Douglas Road from highway traffic.
Please note that construction schedules are subject to change.
Wednesday, April 12, 2021
During the week of May 10, 2021, crews will work in the following area:
- From the southern project endpoint near Miller Road South and the railroad tracks to 96th Street near West Point Douglas Road. Crews will begin natural gas installation activities.
During the week of May 17, 2021, crews will work in the following areas:
- From the southern project endpoint near Miller Road South and the railroad tracks to 96th Street near West Point Douglas Road. Crews will conduct natural gas line installation in this area.
- West Point Douglas Road, between Islay Avenue and 96th Street. West Point Douglas Road will be closed to through traffic. Local traffic will be allowed, and sites will remain accessible.
- West Point Douglas Road, between Jamaica and Islay avenues. Short-term shoulder closures and shifting lanes will occur for natural gas line installation. Local traffic will be allowed, and sites will remain accessible.
- Highway 61/Highway 10, between Jamaica Avenue and halfway between the Jamaica and Keats avenues exits. Short-term shoulder closures and shifting lanes will occur for crews to install concrete barriers along the southbound shoulder of Highway 61/Highway 10. The barriers will separate crews working on West Point Douglas Road from highway traffic.
Please note that construction schedules are subject to change.
April 16, 2021
We want to thank everyone who attended our virtual open house on April 14th to learn more about the project.
If you were unable to attend the virtual open house, you can view the presentation here. If you have additional questions, do not hesitate to contact us.
This year’s construction activities will start in May 2021 and will take place near Highway 61/Highway 10 between 96th Street and Scott Boulevard. As we approach the start of construction, we will provide additional updates. Please note that construction schedules are subject to change.
April 5, 2021
You’re invited to our virtual open house!
We will host a live virtual open house. You can participate through our website or by calling the dial-in number below. The virtual open house will include project information on what you can expect in 2021 and an opportunity for us to answer your questions.
- Date: Wednesday, April 14, 2021
- Time: 6 p.m. – 7 p.m.
- Access Link: click here
- Dial-in Number: 855-962-1519
Can’t make it? We’ll post a copy of the presentation on our website following the live event. If you’d like to receive a hard copy of the presentation, please contact us.
March 2021
Xcel Energy will replace 5.5 miles of natural gas line near Highway 10/Highway 61 in Cottage Grove and St. Paul Park. The South Washington Natural Gas Project will connect to aboveground regulator stations which regulate natural gas pressure.
Construction will begin this spring and continue through fall 2022. During 2021, we expect to work in the following areas:
- West Point Douglas Road
- East Point Douglas Road
- Belden Boulevard
- Hastings Avenue
Please note that construction schedules are subject to change.
Throughout the project, we will communicate with you including through this website. If you have questions or need information, contact us.